Scaffolding around the rear extension of a terraced house at shell stage, with timber and boards in the garden

Renovation and building work in Ghent

We renovate Ghent houses, layer by layer.

Rear extensions, roofs, façades and floors for terraced and town houses in Ghent and the surrounding villages. We draw your house in section first, so you can see beforehand which layer we open up and what goes into it.

Section through a terraced houseThe new layers in the roof, walls, floor and windows are marked in yellow: work in progress.±0.00+3.10+6.05+8.90+13.87-0.15living roomkitchenbedroombathroombedroombedroomatticstreetgarden9.603.102.952.850123m
Project
Rear extension, terraced house, Gentbrugge
Photo
site week 7
Scale
1:50
Status
In progress
ProjectSchietlood · Renovation and building work in Ghent
Title

Project file

Sheet1/7
Scalen/a
Date12-10-2026

Example project

A rear extension in Gentbrugge, week by week

This is how we keep track of a build: every Friday a short report with photos of what happened that week. This terraced house from 1932 got a full-width rear extension, a new load-bearing structure and a kitchen opening onto the garden.

House
Terraced house from 1932, two bays wide
Work
18 m² extension, steel beams, new joists, sliding doors
Duration
14 weeks on site
Budget
€72,000 to €89,000, incl. 6% VAT

Example prices, including 6% VAT: the reduced rate for renovating a private home at least ten years old. A real price follows the survey and is itemised in the quote.

  1. Week 1–2

    Strip-out

    Ceilings down, old pipes and cables out, plaster off to the brick. Only then can we see what the joists and walls are really worth. What we find goes into the first site report, with photos.

    A room being stripped out: open ceiling with old insulation, bare brick, a ladder and materials on the floor
  2. Week 3–5

    Back wall open, steel in

    The back wall comes out across the full width. Props carry the first floor until the steel beams sit on their bearings. The structural engineer sizes the beams and we fit them.

    Props and steel beams under the opened-up rear wall
  3. Week 6–8

    Shell of the extension

    New foundations, block walls and scaffolding round the extension. The neighbours get a note in advance with the days we will be noisy.

    The back of the house with scaffolding, ladders and timber stacked in the garden
  4. Week 9–10

    Joists and flat roof

    The new timber joists rest on the steel. On top go the roof boards, the vapour barrier and 20 cm of insulation under the roof covering.

    New timber joists on a steel beam, seen from below in the stripped-out back room
    New steel beams and timber joists over the ground floor of the extension
  5. Week 11–14In progress

    Glazing, services, finishing

    The sliding doors are in, the ceiling is boarded and the pipes for the kitchen are ready. Still to do: floor insulation, screed and the join with the existing house.

    Inside the new extension: exposed joists, block walls and wide sliding doors to the garden

Other jobs in brief

Other jobs, with district, house, work, duration and example budget
DistrictHouseWorkWeeksBudget (example)
LedebergWorker's cottage, around 1910Roof insulated from inside, new roof window3€15,000 to €20,000
Sint-AmandsbergTown house, 1925External insulation on the back wall, rear windows, ventilation7€44,500 to €58,500
MariakerkeSemi-detached house, 1968Cavity fill, floor insulation, heat pump6€40,000 to €53,000
Brugse PoortTerraced house, 1905Full renovation with extension and new stairs28€200,000 to €260,000

Example prices, including 6% VAT.

ProjectSchietlood · Renovation and building work in Ghent
TitleSection AA
Sheet2/7
Scale1:50
Date12-10-2026

Draw your own house.

Choose your type of house and what you want to change. The cross-section drawing adds each choice as you make it, and a band on the EPC scale shows roughly where your house could end up.Choose your type of house and what you want to change: the section drawing follows.

Indicative. The real label is on the EPC made by an energy assessor.

Section of a terraced house, built before 1946The house as it is, without any work.±0.00+3.10+6.05+8.90+13.87-0.15living roomkitchenbedroombathroombedroombedroomatticstreetgarden9.603.102.952.850123m
Indicative, on the EPC scaleHow we estimate this

Choose the type of house and the period first.

What is drawn in blue

Nothing yet. Choose measures in questions 3 to 5.

What type of house do you have?

Choose the closest type. The drawing adjusts straight away.

What type of house do you have?

Names and dating as in the Flemish heritage inventory (Inventaris Onroerend Erfgoed); the dating of the semi-detached house comes from TABULA.

Choose a type of house first.

Clay model of a piece of old brick outer wall with raw plaster, in section, with seven grey blocks for the EPC scale beside it, F to A+. A brass plumb bob hangs above the current label; the target label is orange.Clay model of a piece of old brick outer wall with raw plaster, in section, with seven grey blocks for the EPC scale beside it, F to A+. A brass plumb bob hangs above the current label; the target label is orange.
Illustration: a wall insulated layer by layer, and a terraced house from before 1946 climbing from label E to B with every measure in the planner above.
ProjectSchietlood · Renovation and building work in Ghent
Title

How we estimate this

Sheet3/7
Scalen/a
Date12-10-2026

The band is a rough estimate based on published rules. Below is how we calculate it, with the sources. For your plan we always show at least two labels, because your house can differ from a typical one.

What this planner does not do: show a grant amount, give a price or promise a label. The real label comes from an EPC made by an energy assessor.

  1. 1Starting point

    Without a label we take the average EPC score of single-family houses from your construction period (EPC database, 2020). A terraced house uses about 0.8 times as much as a semi-detached one (TABULA). A house that has not been renovated usually scores worse than that average, because the average includes renovated houses. So we use 0.8 to 1.05 times the average for a terraced house, a town house or a worker's house, and 0.95 to 1.2 times for a semi-detached one. If you know your label, we start from that label.

  2. 2Heat loss

    For each part: the area from the drawing times the U-value. Today's U-values come from the TABULA typology for each period. Ventilation is the same before and after: we count no gain from airtightness.

  3. 3After the works

    About 90 percent of the score is space heating. That part falls in proportion to the heat loss. For a heat pump we use a primary energy factor of 2.5 for electricity and a seasonal performance factor (SPF) of 2.5 to 3.5, lower in a house that is not insulated.

  4. 4Range

    The favourable end of the band uses the best values, the cautious end the worst. Both ends are converted to labels. If the band with your plan falls within one label, we also show the worse label next to it.

Calculation rules and sources

The scale carries two marks from official sources. Label D is the minimum for anyone who bought a home with label E or F since 1 January 2023 (renovation obligation). Label A starts at 100 kWh/(m² year), the Flemish 2050 target printed on the EPC.

Starting point by construction period
BuiltAverage EPC score (Flemish Energy Agency, VEA, 2020)Terraced houseSemi-detached house
Before 1946538E/FF
1946-1970539E/FF
1971-1985406D/ED/E
1986-1995322C/DD
1996-2005233B/CC
After 2005182BB/C
U-values in W/(m²K): now and after the works
PartBefore 19461946-19701971-19851986-19951996-2005After 2005After the worksTarget on the EPC
Roof1.71.90.850.850.60.30.16 to 0.240.24
Façades2.21.7110.60.4inside 0.35 to 0.45; outside 0.20 to 0.26; cavity fill 0.54 to 0.700.24
Floor0.850.850.850.850.70.40.20 to 0.240.24
Windows553.53.53.521.2 to 1.51.5

U-values now: TABULA (VITO), by construction period. After the works: our calculation for the drawn build-up.

Where a terraced house from before 1946 loses heat today

  • roof 23%
  • façades 30%
  • windows 20%
  • floor 8%
  • ventilation and draughts 18%
  • front door 1%

Check: for a terraced house built before 1946 with the renovation package from TABULA, our calculation gives 137 kWh/(m² year) and TABULA itself 120. Our estimate is slightly more cautious.

ProjectSchietlood · Renovation and building work in Ghent
Title

How we work

Sheet4/7
Scalen/a
Date12-10-2026
Detail: timber joists resting on a steel beam
Site week 9: the joists are on the steel.

How a renovation with us goes

From the first visit to the new EPC you deal with one site manager. These are the steps, with the deadlines we set ourselves.

  1. First visit

    at your house, about an hour

    We walk through the house with you, from cellar to attic, and read your EPC if you have one. You hear straight away what is feasible and what we would tackle first.

  2. Survey

    within two weeks

    We measure the walls, windows, roof slopes and floor heights. With those measurements we draw the section you will find again in the quote.

  3. Itemised quote

    three weeks after the visit

    Every item priced separately, with material, thickness and quantity, so you can compare and work in phases. If the work needs planning permission, as most extensions do, we work with your architect.

  4. Schedule

    before we start

    You get a week-by-week schedule. It also shows when you will be without water, power or a kitchen for a while.

  5. On site

    a report every Friday

    The site report shows in photos what happened that week, including what will later disappear behind the finishes. With questions you call or e-mail the site manager, who answers the same working day.

  6. Handover

    together, with a list

    We walk round the site together and note what still needs doing. You get the invoices and the contractor certificates for your grant. An energy assessor then draws up the new EPC.

ProjectSchietlood · Renovation and building work in Ghent
Title

Materials

Sheet5/7
Scalen/a
Date12-10-2026

The hatching in the section and what they stand for.

Blue always means new work and your choices.

  • Masonry

    Existing façades, inner walls and cellar.

  • Concrete

    Floor slabs and foundations, and the lintels above the windows.

  • Timber in section

    Joists, rafters, purlins and old window frames, drawn with a cross.

  • Earth

    Below ground level.

  • Existing insulation

    What is already there, by period according to TABULA. In ink, because it stays.

  • New flexible insulation

    Mineral wool in the roof (24 cm) and on the inside of the street façade (8 cm). Target on the EPC: U 0.24 W/(m²K).

  • New rigid insulation

    PIR under the screed (10 cm) and boards on the outside of the back façade (12 or 14 cm), finished with render.

  • Cavity fill

    Blown-in beads in an empty cavity. The U-value falls from 1.7 to about 0.55. That does not reach the 0.24 target, so the EPC recommends extra insulation inside or outside.

  • New window

    Insulating glass with Ug 1.0 in a new frame. Target on the EPC for a window: U 1.5.

ProjectSchietlood · Renovation and building work in Ghent
Title

Grants and certificates

Sheet6/7
Scalen/a
Date12-10-2026

For most of the work we do, you can apply for Mijn VerbouwPremie, the Flemish government's renovation grant. How much you get depends on your income, the kind of work and the date you apply. New rules have applied since 1 March 2026, mainly for the two highest income categories.

That is why we give no amounts here. The government's own calculator works with your details.

What we fill in for you

For almost every category of work, the contractor fills in and signs a certificate, from roof insulation to a heat pump. We do that at no extra cost. The invoice lists, item by item, what the grant application asks for.

Renovation obligation

Did you buy a home with an E or F label on or after 1 January 2023? It must reach at least label D within five years of the purchase. The planner shows that line on the EPC scale.

ProjectSchietlood · Renovation and building work in Ghent
Title

Book a site visit

Sheet7/7
Scalen/a
Date12-10-2026

Tell us briefly what you want to change. We will call or e-mail you within two working days to arrange a visit.

For example the year it was built, what has already been done and when you would like to start.

This form needs JavaScript. On this sample site it sends nothing.

Office
Ghent
Opening hours (example)
Monday to Friday07:30 – 16:30
Saturdaysite visits by appointment
Sundayclosed
Where we work
Ghent and the surrounding area: Gentbrugge, Ledeberg, Sint-Amandsberg, Mariakerke, Drongen, Destelbergen and Merelbeke-Melle.